电力工程铁塔攀登或转位防高坠安全防护措施
作者 李国栋
发表于 2024年7月

摘 要: 高处坠落属于一种发生频率较高的事故类型,主要是在电力工程铁塔攀登或转位过程中,由于安全防护不到位和人员误操作而引起的。对电力工程铁塔攀登或转位过程中作业安全设施使用时存在的问题进行了分析,以技术要求、安全规定为依据,对现有防高坠安全防护措施进行了优化与完善,以期为电力人员合理使用防坠装置和做好铁塔攀登、转位时的安全防护提供参考。

关键词: 电力铁塔 攀登或转位 高空作业 防高坠

中图分类号: TM75文献标识码: A文章编号: 1679-3567(2024)05-0091-03

Safety Protection Measures to Prevent Falling From Heights During Power Engineering Tower Climbing or Repositioning

LI Guodong

Ningxia Power Transmission and Transformation Engineering Co., Ltd., Yinchuan, Ningxia Hui Autonomous Region, 750001 China

Abstract: Falling from a height is a high-frequency type of accident, which is mainly caused by inadequate safety protection and personnel’s misoperation during power engineering tower climbing or repositioning. This article first analyzes the problems existing in the use of operation safety facilities during power engineering tower climbing or repositioning, and then based on technical requirements and safety regulations, optimizes and improves existing antifalling safety protection measures, in order to provide reference for power personnel to reasonably use anti-falling devices and do a good job in safety protection during tower climbing and repositioning.

Key Words: Electric power tower; Climbing or repositioning; High-altitude operation; Fall prevention电力工程铁塔检修作业开展过程中,需要工作人员攀登到指定位置进行相关操作。当前,部分工作人员的安全意识不足、作业安全设施不完善、使用操作不规范,容易出现高处坠落的情况,从而造成人员伤亡。为保证电力工程高处作业的安全性,根据铁塔上下攀登作业的安全技术规定和高空作业特点,制定专门的防高坠安全防护措施,优化作业方案,规范安全设施使用。同时,要不断改进铁塔防坠落装置,从而实现对作业人员安全的有效保护。

1 电力工程铁塔攀登或转位时作业安全设施与使用问题

电力事业快速发展过程中,电力工程建设、运维管理中运用的技术手段更为多样。目前,电力铁塔的攀登人员所用的安全防坠设施设备主要有速差器、自锁器和大挂钩等。

1.1 速差器

速差器作为一种常用的防坠器,在高空作业员出现意外坠落的情况时可以保障人员安全,能够在限定的距离内快速制动锁定坠落人员,终止人员下坠。